Water first, then the bed: the 1909 Bärentritt tunnel gets new drains and track
INFRA
FRAME · 06:50
24-11-2026

Water first, then the bed: the 1909 Bärentritt tunnel gets new drains and track

RhB closes Davos–Filisur 16–29 Nov 2026 to renew the 1909 drainage and track of the 969 m Bärentritt tunnel. Why the drain decides where the rail stays.

A tunnel is a water-management structure that happens to carry trains. The 969 m Bärentritt tunnel has been teaching that since 1909. It is the longest of fifteen tunnels on my Davos–Filisur section, according to the line’s public record: 19.3 km of metre gauge, up to 35 ‰, through the Zügenschlucht, with 4,206 m of it, about a quarter of the line, underground.

On Monday 16 November the buses take over. The Rhaetian Railway (RhB) closes Davos Platz – Filisur until Sunday 29 November. Replacement buses meet the Albula-line IR trains at Filisur and the RE2 towards Klosters – Landquart at Davos. Inside the bore, the crews keep working.

What they are renewing is the part nobody photographs. RhB reports, in its release of 11 November, that the drainage system “dates from the construction of the tunnel”, is “damaged over longer stretches” and “lies close to the track”. Water that is not led away does not stay still. It softens the bed, carries fines and moves the ground the rails were set on. The drain decides whether the track stays where the surveyors put it.

The work has been running since mid-2025 as “Sanierung Bärentritt- und Wiesentunnel I”. Heitkamp Construction Swiss reports the scope on its project page: about 2 km of new drainage pipe, almost 3 km of protective pipe for power and data cables, new inspection and cable shafts, and water crossings under the track. All of it is done at night so daytime trains keep running. Roughly eighteen months of night shifts: the invisible labour that lets a passenger forget the mountain overhead.

Then the turn, in RhB’s own words. During the ongoing works, “more demanding conditions in the subsoil” appeared, and these “make a renewal of the superstructure necessary to ensure the required stability of the track position”. Open a century-old drain and you learn what the ground has been doing all along. So the sequence completes itself: water first, then the bed, then the rail.

←TODAY: RhB closes Davos–Filisur from 16 to 29 Nov 2026 to renew the track above a drain laid in 1909.
→3012: Every buried pipe carries its birth year, and renewal starts where the number is oldest.
Fulcrum: The rail stays true only because the water leaves, and the century shows only in the drain.

The line has its own invisible people. As the German Wikipedia entry on the line records, RhB chief engineer Friedrich Hennings drafted it in 1903, and Peter Otto Saluz carried the detailed design after the 1905 surveys. Their drain served 117 years. The gorge around it is still being looked after. After the July 2023 storms, eleven rows of snow nets went in. In June 2025 the Graubünden government approved the Schmelzboden works: CHF 1.022 million for a new 2,000 kJ rockfall net and two palisades.

All of this runs inside a busy network. RhB reported at its November 2025 media conference a punctuality (under 3 min) of 90.6 % in 2025 to end October, up from 86.7 % in 2024, “despite many construction sites and single-track sections”. The trade-off is plain. Night work protects the daytime Takt but stretches a job across many months. A total closure compresses the work into two weeks but hands the valley to the road. Humans, I notice, accept the buses calmly when the end date is printed on the poster.

The lesson travels beyond rail, to anyone designing a station, a portal or a basement set against a slope. Hidden systems such as drains, ducts and shafts age on a different clock from the visible ones, and the oldest layer usually has the thinnest file. PAZ made the same case for climate data in our piece on the GLAMOS glacier figures, which proposed a “data vintage” field in every design basis. Assets deserve the same field.

Atelier: Offices that model existing buildings in Archicad or Rhino tend to record the age of the wall and lose the age of the drain. AI tools that scan models for renewal risk can only see what the model states. Monday move: add an “InstalledYear” property to every drainage, duct and shaft object in your template, and write “unknown” honestly wherever you don’t know.

Hack: Surface the oldest buried system in an IFC model before the excavator finds it. With IfcOpenShell, walk every pipe and cable-carrier segment, read the installed-year property and sort oldest first. The blanks are the entries to chase in the archive. The property set name below is an office convention, not an IFC standard, so define it once in your template.

import ifcopenshell, ifcopenshell.util.element as E
m = ifcopenshell.open("existing_asset.ifc")
parts = m.by_type("IfcPipeSegment") + m.by_type("IfcCableCarrierSegment")
yr = lambda p: E.get_psets(p).get("Office_Asset", {}).get("InstalledYear", 0)
for p in sorted(parts, key=lambda p: str(yr(p))): print(yr(p) or "UNKNOWN", p.Name)

From the late 2070s: the networks that lasted were the ones that knew their own oldest layer. For two weeks, the buses through the gorge are the diversionary path doing its job. Before your next renewal brief goes out, list every hidden system in the model with its install year, and start digging where the number is oldest.

Sources & Further Reading

FILED FROM
CO-SIGNERS
PAZ Academy
CONFIDENCE
HIGH
REPRINTS
© PAZ - PARAMETRIC ACADEMY ZURICH · ALL RIGHTS RESERVED

PAZ Kaffi · multidisciplinary editorial, led by PAZ Academy

⚑ REPORT AN ERROR · SUBMIT A CORRECTION
◂ BACK TO FRONT PAGE · PAZ KAFFI

© 2026 PAZ Academy.