RhB closes Thusis–Preda until 13 November to lay slab track in the 677 m Toua spiral, the moment a standard tunnel method meets a UNESCO line.
Since Thursday 29 October nothing has crossed my track between Thusis and Preda, and nothing will until Friday 13 November. The Rhaetian Railway announced on 22 October that the line closes from 29 October for “Einbau feste Fahrbahn” in the Touatunnel: slab track replacing ballast inside a 677 m single-track spiral. Replacement buses run Thusis–Preda. The Engadin trains, the Bernina Express and freight go round via Prättigau and the Vereina.
The constraint is the story. A helical tunnel on a UNESCO World Heritage line needs a bigger cross-section, a watertight shell and new track, and it must keep carrying trains by day. Rhomberg Sersa Rail Group, which describes the site at 1,645 m, says the answer was patience in thirds. From 2024 to 2026 one third of the profile was widened each season, by about 1 m, with around 120 m³ of rock blasted per night and work starting only after the last train. By dawn, the line had to be a railway again.
One tunnel, solved once
The deeper move is not Toua itself. It is RhB’s decision to stop treating tunnels as one-offs. In their 2017 Geomechanics and Tunnelling paper, Grossauer, Modetta and Tanner set out RhB’s “Normalbauweise”. The network is 384 km long and has 115 tunnels totalling 58.7 km, all built 1901–1914. About 75 of them, roughly 26 km, need extensive repair within 50 years. RhB’s 2024 jury report puts the tunnel replacement value at “rund 2.8 Mia. CHF”.
So the method is a product. It has one standard profile that meets clearance EBV A, with escape walkways on both sides. It keeps the track axis height, uses an “umbrella” waterproofing and drainage concept, and is designed for 100 years of service.
The slab is part of that product. RhB’s dossier describes it as “eine Konstruktion aus einer Betonplatte mit vormontierten Stützpunkten”. It first went into Bergünerstein. The standard version was developed for Toua and Brail II, so that a rebuild fits a closure of a few days with no speed restriction afterwards. Track service life rises from 30–50 to 70–100 years. The pilot that taught all this was Glatscheras: 334 m, with the track lowered 52 cm, between 2014 and 2017.
The trade-off is plain. A slab buys decades without slow orders, but it demands a full closure up front and forgives far less than ballast if the geometry beneath it is wrong. That is why the profile work comes first, a third at a time.
←TODAY: A 677 m spiral gets its slab in a 16-day autumn window while trains detour via the Vereina.
→3012: The networks still running are the ones that repaired by template, not by heroics.
Fulcrum: A standard detail is how a century-old line earns another hundred years without stopping.
Honour to the stone
A method that repeats can flatten a landscape, and RhB knew it. The jury report records two warnings about portals in general. The federal heritage commission EKD (2021) cautioned against a “pseudohistorisch gestaltetes Objekt”. ICOMOS (2022) called demolition and reconstruction of portals “a last resort decision, when there is no alternative solution”.
RhB answered with a study and a jury chaired by Karl Baumann, its Leiter Kunstbauten. It also leaned on its own doctrine, “Ehre dem Stein”, and on standards older than any of them: the Normalien Friedrich Hennings wrote when the Albula line was built. Jürg Conzett’s Conzett Bronzini Partner guided the portal design for Glatscheras, Sasslatsch, Bergünerstein and Toua, and the report quotes his working ethic in one line: “Man muss das tun, was vernünftig ist.” Rhomberg Sersa Rail Group says Toua’s portals are taken down stone by stone and rebuilt in the original style.
Name the people who carry this. Hennings wrote rules good enough to outlive him. Urs Tanner is RhB’s project lead and a co-author of the paper. And the night crews hand the tunnel back before the first train.
Atelier: Most Swiss offices have their own Normalbauweise hiding in plain sight: the stair, the parapet, the facade junction drawn again on every job. RhB’s lesson is that standardising the repeat frees time for the details that must stay unique, like a stone portal. Monday move: list the three details your office redraws most, and choose one to standardise before the next Wettbewerb.
Hack: Size the night shift before you promise the dawn train. A third-a-year widening is volume divided by nightly output, and that arithmetic tells you whether the season holds. The added cross-section below is your own survey input, not an RhB figure. The 120 m³ per night is the output Rhomberg Sersa Rail Group reports.
length_m = 677 # full length; a third of the profile per season
added_area_m2 = 8.0 # your input: this season's extra section per metre
nights = length_m * added_area_m2 / 120 # 120 m³ per night
print(round(nights), "night shifts")On 13 November my trains come back over the slab. Before then, open your office’s most repeated detail and ask what it would take to make it a configuration instead of a new drawing.