The Wall Is a Path: A 26 m Arm Prints a Four-Storey Office in Tyrol
NELCON's mobile INSTATIQ arm prints unreinforced load-bearing walls in Weerberg straight from the model. What it means for walls in your Rhino model.
A standard truck mixer backs up to a site in Weerberg, Tyrol, and its concrete goes into a print head at the end of a 26 m robot arm instead of into formwork. Layer by layer, each up to 10 cm high, the ground-floor walls of the NOBUGS GROUP headquarters are rising. The arm is the Progress One from INSTATIQ, a spin-off of the Putzmeister Group. It is run by NELCON, a joint venture of the STRABAG group and INSTATIQ, and STRABAG builds the rest of the shell. Strabag calls the four-storey building Austria’s tallest 3D-printed building. Printing runs until January 2027, and completion is due in March 2027.
The physics is old and honest: concrete is strong in compression. The Block Research Group at ETH Zurich and Zaha Hadid Architects’ computation group showed with Striatus in 2021 that unreinforced printed concrete carries real load when the geometry keeps it in compression. Weerberg is a different team with a different job, flat walls under vertical load, but the structural reading holds. As top.tirol reports, the printed walls are made “mit unbewehrtem Beton, also ohne Stahleinlagen” (in unreinforced concrete, without steel inserts), and about 80–90 % of the walls are printed. Per ingenieur.de, the conventional reinforced concrete walls “dienen der Aussteifung des Gebäudes” (serve to brace the building) against loads such as wind. Gravity goes to the printed walls, wind to the cast ones.
The drawing becomes the toolpath
Per ingenieur.de, the building model fixes wall runs, windows and fixtures, and “eine Software übersetzt diese Daten in die Bewegungen des Druckkopfs” (software translates this data into the movements of the print head). INSTATIQ’s own description, reported by Gulf Construction in 2025, gives print layers up to 30 cm wide and 10 cm high, with aggregates up to 10 mm. PAZ made the same argument for brick in A Wall Is a List: once a machine lays the material, the wall stops being a hatch and becomes data.
Strabag gives about 682 m² of wall from about 179 m³ of concrete over 18 print days in four phases, and ingenieur.de is precise that the 18 days cover printing only. By our own arithmetic, that is about 38 m² of wall per print day. INSTATIQ lists the P1 at 10 cm/s with a 60-minute setup. From where my tracks sit, setup matters more than reach: “Wir setzen den Drucker für jede Ebene neu um” (we reposition the printer for every level), says Chris Brandstätt, managing director of NELCON. Each storey means a new origin for the model.
←TODAY: A mixer-fed 26 m arm prints 682 m² of unreinforced load-bearing wall for a company headquarters in Tyrol.
→3012: Every wall in the Zurich-3012 model carries its own path, and the as-built log is simply the print log.
Fulcrum: The model has to say which walls carry gravity and which brace against wind, because the robot builds only the first kind.
The finish is decided at the nozzle
top.tirol reports that NELCON normally runs three people plus the machine, against four to five for a masonry crew. Weerberg needs four, “weil die Wände nicht verputzt werden, sondern sichtbar bleiben” (because the walls are not plastered but stay visible). Strabag plans enclosures and tempered concrete to secure early strength; ingenieur.de adds that printing is allowed down to 0 °C by day, with fresh walls under insulation mats on nights no colder than −5 °C.
Strabag claims doubled wall speed, halved staffing, load-bearing walls up to 20 % thinner and up to 40 % less CO₂ than calcium silicate masonry, depending on the mix. Brandstätt, per top.tirol, puts the cost at masonry level. These are the builder’s own figures, and until independent measurement confirms them, they stay claims.
The rulebook is catching up
The clients wanted this. Ajdin Gazija and Christian Machalitzky, founders and managing directors of NOBUGS, call 3D concrete printing “ein absoluter Wunsch von uns” (an absolute wish of ours). Mario Gerber, Tyrol’s Landesrat for business, tourism and digitalisation, says such investments “schaffen Wertschöpfung” (create value), and per top.tirol his department supports the project with innovation funding. top.tirol notes that no dedicated standards exist for 3D-printed buildings, and approval took a fourth submission; Gazija admits to “ganz viele weiße Haare” (a lot of white hairs). ingenieur.de, citing ORF Tirol, reports that fire protection moved some parts into conventional reinforced concrete. That gap belongs to the rulebook, not to the people who brought it a real building. A Swiss office taking a printed wall to a Baubewilligung should expect the same questions.
The lineage is short and steady: a one-storey Strabag office extension of about 125 m² in Hausleiten in 2021, then Züblin and INSTATIQ printing the top floor of a four-storey GWG Reutlingen block in Metzingen in four days in 2025, now Weerberg. The Union Grafenwörth tennis clubhouse is next. The units that lasted in my time were the ones a crew could reset by hand, and a mobile arm moved storey by storey by four people is that kind of unit.
Atelier: A Zürich studio drafting a mid-rise in Archicad or Rhino draws load-bearing and bracing walls as the same kind of object, so the difference lives in an engineer’s note. A printer needs it in the geometry. Monday move: put every wall you might print on its own layer as a centreline with thickness and openings, and keep the reinforced bracing walls on a separate layer.
Hack: Read the print path straight off your Rhino model before anyone quotes you a print schedule. Put the centrelines of the walls you intend to print on a layer called PRINT_WALLS, in metres, and run this in Rhino’s ScriptEditor. It sums one layer’s path length and converts it to head travel time at INSTATIQ’s published 10 cm/s. Multiply by your own layer count and you see whether the plan is a three-day or a three-week job.
import rhinoscriptsyntax as rs
walls = [w for w in rs.ObjectsByLayer("PRINT_WALLS") if rs.IsCurve(w)]
L = sum(rs.CurveLength(w) for w in walls) # metres of path per layer
print("%.1f m per layer, %.0f s at 10 cm/s" % (L, L / 0.10))The PAZ Grasshopper↔Archicad Library can carry that layer split into Archicad, so printed and cast walls keep their roles across both programs.
Sources & Further Reading
PAZ Kaffi · multidisciplinary editorial, led by PAZ Academy