One Rulebook, One Levy: Switzerland's Proposed GFM 2028 Funds Heat Systems That Perform
Switzerland's proposed GFM 2028 merges two building subsidies into one, paid from the CO2 levy, and funds only heat pumps whose SCOP beats the market.
A heat pump obeys one equation before it obeys any ordinance. Its ceiling is the Carnot limit, Thot / (Thot − Tcold), so every kelvin you take out of the temperature lift buys efficiency for free. The draft rulebook now on the table in Bern takes that equation seriously. On 28 October 2026 the Federal Council opened consultation on a change to the Energy Ordinance (EnV) that proposes one Swiss building subsidy in place of two. Responses are due by 11 February 2027, and the proposed entry into force is 1 January 2028.
The essence is three words long: one programme. The Gebäudeprogramm under the CO2 Act and the Impulsprogramm under the Energy Act merge into the Gemeinsames Fördermodell, GFM 2028. The cantonal energy directors’ conference, EnDK, approved the draft on 28 August 2026. It has one rulebook and one source of money: the earmarked share of the CO2 levy, following Parliament’s Entlastungspaket 2027, which ends co-funding from the general federal budget.
The number that moves the spec
The explanatory report from the federal energy department (UVEK, Erläuternder Bericht) proposes paying for heat pumps only when their SCOP, the seasonal coefficient of performance, beats the market. The thresholds come from a July 2026 market analysis. In the small-output segment, where most units are sold, only roughly the best 20 to 30 % of devices would qualify. The reason is winter electricity: a seasonal figure weights the cold months, exactly when the Swiss system is shortest.
The report calls the idea “Systemdenken anstelle von Gerätedenken”: system thinking in place of device thinking. Energy and power management systems (EMS) are now explicitly included. The draft funds thermal regeneration of borehole fields, heat returned to the rock in summer so dense probe fields do not cool year after year, and adds an extra incentive for boreholes deeper than 500 m. That is physics on the subsidy form. The ground warms by roughly 3 K per 100 m, so a deeper probe works against a smaller lift.
←TODAY: A proposed Swiss subsidy pays for measured seasonal performance, not for owning a heat pump. →3012: Buildings are financed by the lift they avoid, and the ground is managed as a seasonal battery. Fulcrum: The SCOP on a data sheet is the contract between thermodynamics and public money.
Wood, networks, envelope
Under the draft, wood heating below 70 kW is funded only where no heat network, no ground- or water-source heat pump and no efficient air-source unit is feasible. Above 70 kW it is funded for peak load only. The report notes the point is debated among cantons. A heat-network connection qualifies at 70 % fossil-free heat, following MuKEn 2025; new heat plants must run on 100 % renewables or waste heat.
Comprehensive renovations would need to reach at least GEAK class D, with remaining heating demand covered entirely by renewables or waste heat. Minergie, including the new Minergie-Netto-Null, stays eligible. Cantons may add a bonus for components rated at least eco2 on the Ecobau list. Combined federal and cantonal support would be capped at 50 % of total investment.
The money, stated plainly: about CHF 450–600 million a year flows today across both programmes. The draft sets a ceiling of CHF 410 million a year until the end of 2034, paid to the cantons as Globalbeiträge. The trade-off is real: a smaller pot under stricter rules means fewer, better projects, and fewer owners funded for a mid-market unit. The report expects “kein Wirkungsverlust”, no loss of effect, from Parliament’s changes and stricter rules that follow the Swiss Federal Audit Office’s report 23316, which recommended cutting Mitnahmeeffekte, grants paid for work that would have happened anyway.
Atelier: For a Zürich renovation studio or an HLK engineer in Bern, the heat-pump line in the specification stops being a brand choice and becomes a measured figure the client’s grant depends on. On Monday, add a mandatory “SCOP (EN 14825, at design flow temperature)” field to your office’s heat-pump tender template.
Hack: Show your client why depth and low flow temperature pay. This sketch computes the Carnot ceiling for a 35 °C floor-heating flow against probes of growing depth, assuming about 10 °C at the surface, about 3 K per 100 m averaged over the probe, and a 5 K drop across the exchanger. The values are illustrative physics, not GFM thresholds. It runs unchanged in a GhPython component in Rhino.
T_flow = 273.15 + 35 # supply temperature in K
for depth in (150, 300, 500, 800):
T_src = 273.15 + 10 + 0.03 * depth / 2 - 5 # mean probe temperature in K
print(depth, 'm ->', round(T_flow / (T_flow - T_src), 1))
Real machines reach only a fraction of that ceiling. The ratio between two depths still tells the honest story.
The draft is open to anyone until 11 February 2027. Compare the SCOP of your last three specified units with the annex thresholds, and send the consultation your answer.